Case Study#2: Boeing’s Virtual Fence
On January 14, 2011, Secretary of Homeland Security Janet Napolitano made it official: the
Virtual Fence Project was to be officially canceled. In her statement explaining the decision,
Napolitano cited the difficulty of creating a unified, fully integrated security system and
promised to “pursue a new path forward.” What was left unsaid were the reasons that led
to the final decision—principally, a too-complicated technical system that did not work
and was leading to ballooning costs.
Illegal crossing into the United States along the Mexican border has reached epidemic
proportions in recent years. Fear of drug smuggling, illegal aliens, and possible terrorist
incursions have made the issue of homeland security one of the major “hot buttons” in the
political arena, both in Washington, DC and in states located along the southern border, as
well as those in proximity to Canada. The problem is compounded by the sheer sizes of the
borders involved. The Mexico/U.S border runs for nearly 2,000 miles, much of it across
desert wastelands and other inhospitable and remote areas. Establishing any sort of border
security in the wake of the 9/11 attacks is a national necessity, but it is a daunting and
difficult task.
The Department of Homeland Security (DHS) was organized following the attacks on the
World Trade Center towers, and is charged with the responsibility of securing all borders
and points of illegal entry into the United States in cooperation with Customs and Border
Protection. As part of its mandate, it has developed plans for creating a more secure and
stable border with Mexico to prevent the flow of undocumented immigrants, drugs, and
potential terrorists. For the first stage in this process, DHS proposed a project to physically
and electronically seal the stretch of the desert between the United States and Mexico under
a multibillion-dollar contract named the Secure Border Initiative Net (SBInet). President
Bush in May 2006 called SBInet “the most technologically advanced border security
initiative in American history.” A 28-mile stretch of desert, centered on Nogales, Arizona,
1

was to be the pilot stage in a project that eventually would be used to monitor and control
some 6,000 miles of border with both Mexico and Canada.
In late 2006, Boeing was selected as the major contractor for the SBInet project. Although
better known for its military weapon systems, Boeing’s Integrated Defense Systems Unit
was made responsible for overall coordination of a massive system of towers as well as
listening devices, motion sensors, cameras, and radar to be used to detect and help
apprehend illegal immigrants crossing the border. In fact, the U.S. government chose to
outsource the entire project to private firms, expecting that contractors would design the
program’s elements, build them, and then handle full oversight of their own work.
In a nutshell, the system used a chain of 100-foottall towers that each scanned a 360-degree
radius for a distance of 10 miles. Ground radar sensors also attempted to detect footsteps,
bicycles, and vehicles. The first $20 million pilot phase, named Project 28 after the length
of the part of the desert that it was supposed to cover, was to be completed by mid-June
2007. Boeing selected more than 100 subcontractors to build various components of the
system, with its project managers maintaining overall control of the development process.

Unfortunately, its structure was unwieldy, and the project was further compromised by
the sheer number of distinct elements and technical systems Boeing was attempting to
integrate. The technical challenge of integrating systems including watch towers, sensors,
radar, and specialized cameras was beyond anything Boeing had attempted before. The
problem was particularly noteworthy when we consider that integration, in many ways,
was the project. The various technical elements were difficult but attainable. The challenge
for SBInet lay in the ability of Boeing to find a means to bring all these new and unproven
technologies together under one umbrella. So complicated was the challenge, in fact, that
the virtual fence failed a series of initial tests, significantly delaying the full deployment of
Project 28.

Unfortunately, these technical and coordination problems were never resolved. In the
2

nearly three years after original testing was done on one section of the fence, SBInet had
cost the government $672 million dollars, with the end nowhere in sight. Although the total
project cost was anticipated at $1.1 billion, congressional watchdog groups argued that the
final cost of the project could soar to over $30 billion. Costs, in fact, were a sore point with
the project from the time it was bid. Originally promising to complete SBInet for $1.1
billion, Boeing’s revised estimates went to $2.5 billion and then, just a few months later, to
$8 billion. This rapid escalation of projected costs finally prompted a congressional
oversight committee hearing, in which Boeing endured withering criticism from
representatives who questioned its motives in asking for more money and time to complete
the project. In the meantime, beset by continuing problems, Boeing had also revised its
estimates for the completion date to 2016, more than seven years after the date in the
original plan.

A major concern was Boeing’s pyramid-like management structure that critics said caused
confusion and a lack of clear responsibility. Worse, it made it easier for hidden costs to be
charged to the project. Because Boeing embedded multiple subcontracting layers in the
Virtual Fence development, it was able to add charges at each level. The larger problem
was the clear conflict of interest that emerged by placing Boeing in charge of project
oversight, while allowing them to manage subcontractors and monitor the progress of the
project. Not surprisingly, with this configuration little information came to light about cost
overruns or schedule slippages until quality and overrun problems were simply too large
to ignore . . . or hide.

Admittedly, the problems that sank the SBInet project were complicated and came from
multiple sources. Besides the technical challenges of managing 100 subcontractors, all
required to provide critical components that Boeing would integrate, the project had
effectively shut out most federal agencies and oversight groups. It was difficult to get
accurate project status information given the government’s decision to “farm out” border
security to private contractors. As a result, congressional investigators found that
3

Homeland Security officials were simply standing by while Boeing provided information
that was “replete with unexplained anomalies, thus rendering the data unfit for effective
contractor management and oversight.” Furthermore, many critics questioned the
feasibility of the original intent of the project itself, wondering about the likelihood of ever
effectively sealing a border that runs through some of the most inhospitable terrain in
North America. Whether through a combination of poor oversight, over-optimistic scope
expectations, or simple inability to make this cutting-edge technology work, SBInet
remains an example of a significant program failure at the taxpayer’s expense.

Questions
1. What problems do you see emerging from a project such as SBInet where the
government allows the contractor to determine scope, manage all contractor relations,
and decide how to share project status information with oversight bodies?
………………………………………………………………………………………………………
………………………………………………………………………………………………………
……………………………………………………………………………………………………….
………………………………………………………………………………………………………
………………………………………………………………………………………………………
……………………………………………………………………………………………………….
………………………………………………………………………………………………………
………………………………………………………………………………………………………
……………………………………………………………………………………………………….
………………………………………………………………………………………………………
………………………………………………………………………………………………………
……………………………………………………………………………………………………….
………………………………………………………………………………………………………
………………………………………………………………………………………………………
……………………………………………………………………………………………………….
………………………………………………………………………………………………………
4

2. Consider the following two arguments: “The failure of SBInet was due to poor scope
management” versus “SBInet failed because of poor oversight and project controls.”
Take one side or the other in this argument, and justify your response.
……………………………………………………………………………………………………….
………………………………………………………………………………………………………
……………………………………………………………………………………………………….
………………………………………………………………………………………………………
………………………………………………………………………………………………………
……………………………………………………………………………………………………….
………………………………………………………………………………………………………
………………………………………………………………………………………………………
……………………………………………………………………………………………………….
3. With the current publicity surrounding the intentions of the Trump administration to
begin building a wall along the border with Mexico, identify three lessons from this
case that could help with that development process. In other words, if you were to advise
the Trump White House on major lessons to absorb as it considers beginning its own
fence, what would they be?
………………………………………………………………………………………………………
………………………………………………………………………………………………………
……………………………………………………………………………………………………….
……………………………………………………………………………………………………….
………………………………………………………………………………………………………
………………………………………………………………………………………………………
……………………………………………………………………………………………………….
………………………………………………………………………………………………………
………………………………………………………………………………………………………
……………………………………………………………………………………………………….

5

Purchase answer to see full
attachment

Share This Post

Email
WhatsApp
Facebook
Twitter
LinkedIn
Pinterest
Reddit

Order a Similar Paper and get 15% Discount on your First Order

Related Questions

Description

Description Chapter 1: Description of the company This section should answer the following questions: What is the full title of the company/institution? Give a brief history of the company, full mailing address and relevant weblinks What is the type of ownership of the company/institution? State the main shareholders and their

Description

Description Revise the word file according to the instructor’s comments, and after making the necessary changes, organize it based on the requirements outlined in the attached PDF. Due 8th May 2025 by 11:59 pm. Research Methods and Quantitative Analysis 2nd Semester, 2025 EMBA – Section JA The proposal is worth

Description

Description see ASSIGNMENT COVER SHEET Course name: Health and Environmental Risk Assessment Course number: PHC 351 CRN: Assignment title or task: (You can write a question) Discuss the steps and methods of risk communication and community engagement and support your answer with examples. Student name: xxxx Student ID: xxxx Submission

Description

Description see College of Health Sciences Department of Public Health PAPER ASSIGNMENT Course name: Introduction to Mental Health Course number: PHC-273 Go through the research articles in the link below and answer any one of the following questions in at least 350 words. • • Assignment task Q1. Discuss about

Description

Description HALAH JAMALULDINE Module 14 Collapse Change management is a critical process in healthcare organizations, particularly in Saudi Arabia, where the healthcare system is undergoing rapid transformation to align with Vision 2030. One notable change in a Saudi healthcare organization was the implementation of electronic health records (EHRs) in a

Description

Description Module 14: Rewarding through Performance Management Effective Reward Systems in Performance Management Performance management systems and reward systems are essential components of motivating and driving individual and group performance in organizations. Analyze reward systems and the appropriate application to meet organizational goals. Discuss the different types of reward systems,

Description

Description Reply to discussion (Module 14: Rewarding through Performance Management) Q – Please read the discussion Attached and prepare a Reply to this discussion post with comments that further and advance the discussion topic. The reply needs to be substantial and constructive in nature. it should add to the content

Description

Description Reply to discussion (Module 14: Rewarding through Performance Management) Q – Please read the discussion Attached and prepare a Reply to this discussion post with comments that further and advance the discussion topic. The reply needs to be substantial and constructive in nature. it should add to the content

Description

Description Author(s) Year Study Name Study Type Amponin & Britiller 2023 Electronic health records (EHRs): effectiveness to health care outcomes and challenges of health practitioners in Saudi Arabia empirical, descriptive, and cross-sectional study Alfaleh et al. 2022 The role of telemedicine services in changing users’ intentions for presenting to the

Description

Description Hello, the task is to write a discussion and Quiz for module 14 from MKT640 course

Description

Description I want assistance with my internship report. will give details later 👍🏼 You may use AI to save time, as long as it gives accurate description, I don’t mind it =) College of Administration and Finance Sciences Form No 4- Internship Report Cover Page Student`s name: Student`s ID #:

Description

Description See College of Health Sciences Department of Public Health HCM101-PAPER ASSIGNMENT Course name: Healthcare Management Course number: HCM101 CRN The textbook (Buchbinder & Shanks (2012), second edition, chapter 5) addresses an essential topic in health care, which is strategic planning. SWOT analysis is a significant tool that healthcare leaders

Description

Description Consumer Behavior Case Study: Nike and Maslow’s Hierarchy of Needs Introduction Nike is a global leader in athletic apparel and footwear. Its success can be partly explained by how it meets different levels of consumer needs based on Maslow’s Hierarchy of Needs, which include: 1.Physiological, 2.Safety, 3.Social, 4.Esteem, and

Description

Description Dis. one file. Discuss in detail the process that a researcher hypothetically would go through when they become aware of a population health problem that arises during the Hajj. What research would be needed to protect the population of the Kingdom? reply. Hi Sarah, Great discussion! I agree that

Description

Description The organizational behavior aspects (motivation – attuited – personality – emotion ..etc. ) helps the manger to understand their employees in the work environment In two essays answer the following questions: 1.How those aspects will be effect in the work performance and employee satisfaction? (5 grades) 2.What are some

Description

Description see College of Computing and Informatics Assignment 2 Deadline: Sunday 13/04/2025 @ 23:59 [Total Mark for this Assignment is 8] Student Details: Name: ### ID: ### CRN: ### Instructions: • You must submit two separate copies (one Word file and one PDF file) using the Assignment Template on Blackboard

Description

Description I need help completing a discussion board post for my Management course (Managing Perform. for Results). Below are the exact requirements provided by my instructor: Description: In this module, you will examine how pay and reward structures support and facilitate performance management. You will also compare traditional and contingent

Description

Description Module 14: Discussion ForumModule 14: Dis one One file. Discussion Forum Think about a change you know of in a healthcare organization in Saudi Arabia. How was the change received and what was the outcome? What were the resistance points? Provide and discuss suggestions to deal with resistance to