8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 1 Assignment lecture #3 1. Construct an AON network based on the following: ACTIVITY IMMEDIATE

8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 1

Assignment lecture #3
1. Construct an AON network based on the following:

ACTIVITY IMMEDIATE PREDECESSOR(S)
A –
B –
C –
D A, B
E C

2. Insert a dummy activity and event to correct the following AOA network:

8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 2

Assignment (cont’d)
3. The City Commission of Nashville has decided to build a botanical garden and picnic area in

the heart of the city for the recreation of its citizens. The precedence table for all the
activities required to construct this area successfully is given.

CODE ACTIVITY DESCRIPTION
TIME (IN
HOURS)

IMMEDIATE
PREDECESSOR(S)

A Planning Find location; determine resource requirements 20 None
B Purchasing Requisition of lumber and sand 60 Planning
C Excavation Dig and grade 100 Planning
D Sawing Saw lumber into appropriate sizes 30 Purchasing
E Placement Position lumber in correct locations 20 Sawing, excavation
F Assembly Nail lumber together 10 Placement
G Infill Put sand in and under the equipment 20 Assembly
H Out-fill Put dirt around the equipment 10 Assembly
I Decoration Put grass all over the garden, landscape, paint 30 Infill, out-fill

a) Draw the Gantt chart for the whole construction activity.
b) Draw the AON network for the construction activity.
c) Draw the AOA network for the construction activity.

8/3/2022 By TUY Pheap, OPM Course for MBA, B23, G11 3

Assignment (cont’d)
4. The planning department of an electronics firm has set up the activities for developing and production of a

new MP3 Player. Given the information below, develop a project network using Microsoft Project. Assume a
five-day workweek and the project starts on January 4, 2020.

Activity ID Description Activity Predecessor Activity Time (weeks)

1 Staff None 2
2 Develop market program 1 3
3 Select channels of distribution 1 8
4 Patent 1 12
5 Pilot production 1 4
6 Test market 5 4
7 Ad promotion 2 4
8 Set up for production 4, 6 16

The project team has requested that you create a network for the project, and determine if the project can
be completed in 45 weeks.

Share This Post

Email
WhatsApp
Facebook
Twitter
LinkedIn
Pinterest
Reddit

Order a Similar Paper and get 15% Discount on your First Order

Related Questions

Research Paper Part 1 Post ideas of fraud for approval PART 2 1.

Research Paper Part 1 Post ideas of fraud for approval PART 2 1. Imagine your intent is to make as much money as you can by committing fraud. Give a detailed description of how you would commit this fraud e.g.  individuals, companies and departments involved and impacted by your fraud

see attached  BUSI 675 Application Assignment Instructions Overview

see attached  BUSI 675 Application Assignment Instructions Overview Each application assignment is a comprehensive experiential learning experience and is directly related to business analysis and decision-making. The student will complete four application assignments (4). Instructions Each assignment must be a minimum of 3-5 pages of original discussion and analysis, not

Digital marketing review of the Sparkling Water Industry.  See attached instructions. Digital Marketing and Revenue Project

Digital marketing review of the Sparkling Water Industry.  See attached instructions. Digital Marketing and Revenue Project You will explore eCommerce Marketing through a Google certificate program and explore revenue and sales models. · Consider the Sparkling Water Industry (  https://www.drinkwaterloo.com/,   https://drinkspindrift.com/,   https://www.deerparkwater.com/sparkling-water,   https://www.bubly.com/mix/index.php,   https://www.drinkaha.com/) · Review and analyze the Industry