Hi Good day everyone Really appreciate if you can help me

Hi Good day everyone

Really appreciate if you can help me to solve problem as per details on pict attached, and determine :

(i) Draw the PERT network for the project.

(ii) Prepare the activity schedule for the project.

(iii) Determine the critical path.

(iv) If a 25-week deadline is imposed, what is the probability that the project will be finished within the time limit?

thank you so much for your kindly help